Window Survey
04/07/15 12:10
The window survey took place on Thursday after a furious few days preparation by Liam, Chris and the team. Raising the ground floor meant we had to move most of the cills and the external insulation also forced additional changes to the positions of 3 windows and the rear door. Each change wasn't massive but they all meant time was used up and hitting the survey deadline meant longer days on site. Jon (Ecohaus Internorm) checking some details with Glenys, Chris and Liam.
It was inevitable that some of the installation details needed rethinking on Friday but this was very efficiently handled by Jon and Andrew (Eco arc). Hopefully we can sign off the windows next week before they disappear into the Interterm system for many weeks!
It was inevitable that some of the installation details needed rethinking on Friday but this was very efficiently handled by Jon and Andrew (Eco arc). Hopefully we can sign off the windows next week before they disappear into the Interterm system for many weeks!